Estonian railway seeks contractor for Ida-Viru station works

Friday 27th November 2026 on 06:45 in Estonia

Estonian Railways, Ida-Viru County, railways

Estonian Railways is seeking a contractor for reconstruction work at three stations in Ida-Viru County, including the removal of Auvere station, ERR reported. Work is due to begin in spring and finish by the end of November 2028.

The contractor is expected to be selected in the first half of 2027, said Imre Reipõld, head of construction services at Estonian Railways. The company has not disclosed the estimated cost. The work will be carried out in stages.

Passenger trains last stopped at Auvere in 2012, and its station building and platforms have since been demolished. The remaining switches will now be removed, leaving no station there.

At Vaivara, the station building is to be reconstructed, alongside railway works. In Narva, the station layout will be changed so passenger trains can reach the platform more quickly. Reipõld said most of the work at Vaivara and Narva is linked to railway electrification.

Estonian Railways says curve realignment and a major track overhaul on the Tapa-Narva line, which began in 2022, have been completed. The work cost just over 16 million euros, with 85 percent funded by the European Union.

The overhaul has made it possible to raise the maximum permitted speed for passenger trains from 135 to 160 kilometres per hour. The express train journey between Tallinn and Narva currently takes two hours and 13 minutes. If all required work is completed and operating permits are granted, the journey is expected to take one hour and 50 minutes from June 2027.

The overhead power line has been built along the Tapa-Narva line as far as Narva, while construction continues at the traction substations in Püssi and Oru. Railway signalling system reconstruction is due to start next year, proceed in sections and finish in 2028.