Developers propose 2,900 MW of data centres in Estonia
Saturday 21st November 2026 on 05:30 in
Estonia
Developers have submitted seven applications to connect large data centres to Estonia’s electricity grid, representing a total of 2,900 megawatts, ERR reports. The plans include projects by Estonian and foreign companies, though it remains unclear how many will be built.
Estonia has one large next-generation data centre in operation: a Greenergy Data Centers facility opened in 2022 in Hüüru, near Tallinn. Its current capacity is two megawatts, with peak capacity planned to reach 200 megawatts by early 2028.
Renewable energy company Sunly plans to build a data centre near Risti in Lääne County, with electricity consumption of up to 180 megawatts. Building it at full scale would cost 1.7 billion euros.
Estonian renewable energy developer Evecon is working on a data centre near Lihula with electricity consumption of up to 100 megawatts. The company has also announced plans for a data centre complex near Risti. It has sought planning conditions for projects in Lüganuse municipality and near Kilingi-Nõmme in Saarde municipality.
Norwegian conglomerate Northern Europe Energy Group has also announced plans for a data centre near Lihula. A project in Tapa is being discussed by Estonian companies Sustainable Investments and Sinfra, together with the Finnish Ehrnrooth business family. The investment could reach 3.4 billion euros. Sinfra is also interested in building a centre in Lääne County.
Four potential data centre projects are under consideration in Lääne-Nigula municipality. Sunly and Norwegian company Magnora Data Center are jointly developing a campus near Risti. The project could initially connect 180 megawatts to the grid, with capacity potentially increasing to 400 megawatts if the substation is expanded.
Evecon is also interested in a data centre near Risti. Its proposed planning area covers more than 41 hectares and would include two data centre buildings and up to nine industrial buildings. Planning has also begun for a Sinfra project in Jõgisoo village. Another developer has expressed interest in the municipality, but the proposal is at an early stage and the company has not been named.
Lääne-Nigula mayor Janno Randmaa said Sunly’s plan was further advanced than the others. The developer also operates a local solar park, which Randmaa said would provide cover for the centre’s electricity needs. He said the municipality did not yet know how the other developers planned to meet their energy requirements.
Randmaa said the municipality needed to understand the projects’ electricity and cooling-water consumption before proceeding with planning. The latest three applications had arrived in less than six months, he said, raising questions about whether the interest represented a lasting trend and how many projects would become reality.
Residents have not so far opposed the data centres, but have asked about possible environmental effects, including water use and noise, Randmaa said. He added that more questions were likely as people learned more about the projects.