Riga Eastern Clinical University Hospital is rapidly building a new centre for lung health and infectious disease treatment, with half of the structure completed in four months, LSM reports.
The four-storey building is taking shape behind the hospital’s Gaiļezers clinic. Its concrete wall panels, made in Liepāja, come with insulation, utilities, windows and automatic blinds already installed, speeding up construction. The third floor is now under way, and the hospital hopes to have the roof in place before winter.
The building will include a technical section in the basement, a first floor for infectious patients and a second floor for staff and medical workers. A weather station on the roof will help adjust the blinds to outdoor conditions and maintain the indoor climate, the hospital said.
Engineering utilities dating from 1979 are being rerouted as part of the work. A logistics building is also being built nearby.
The Tuberculosis Centre, currently in Stopiņi, will move into the new building first. The Latvian Centre for Infectious Diseases is expected to move there later.
The contract for the building’s design and construction, worth 69.5 million euros, was signed with the company UPB. A symbolic time capsule was placed in the foundations on July 15.