Politicians split over how Estonia should power data centres

Tuesday 24th November 2026 on 15:30 in Estonia

data centres, energy, Estonia

Seven applications to connect data centres in Estonia seek a total of 2,900 megawatts, far exceeding the country’s current peak electricity demand, ERR reports. Politicians disagree on how to meet the facilities’ power needs.

Data centres need electricity around the clock. If Estonia does not increase generation before they are completed, it will have to import the shortfall through cross-border connections. Large data centres are also planned in Finland, which could reduce the electricity available to Estonia and affect prices.

Developers have proposed building power generation alongside data centres, for example, solar parks. Eesti 200 MP Marek Reinaas said developers were unlikely to build the facilities without certainty that their energy needs could be met. He said data centres would probably be developed alongside power generation.

Reinaas said solar parks paired with energy storage could be a good solution, with a combination of wind and solar power and storage being the most effective. He also said Estonia would benefit from hosting data-processing infrastructure, and that concerns about data centres’ potential electricity and water use should not be excessive.

Centre Party parliamentary group leader Lauri Laats also said data centres were needed in Estonia, but their construction should come with clear conditions. He said the state must ensure existing generation capacity is retained and recognise that current renewable energy production may not be enough to meet demand from large consumers.

Laats said the oil shale sector provides about 1,000 megawatts during peak demand. The rest of Estonia’s electricity, he said, comes mainly through connections with Finland and Latvia and from renewable energy plants. He said data centre developers should cover at least part of their own energy needs, citing a plan by Sunly to combine a data centre development with a solar park and battery storage.

Laats also called for the state to review its energy development plan to account for new large electricity consumers. He said the electricity grid must be developed because it may not currently be able to accommodate such large capacities.

Isamaa board member Priit Sibul said data centres would push electricity prices sharply higher, but argued that Estonia needs large electricity consumers to help cover the costs of maintaining the grid. He said the total electricity bill should be considered, rather than generation and network charges separately, and that adding large consumers could reduce network service costs.

Sibul said solar parks could not meet demand throughout the year. He also cautioned against relying on electricity imports from Finland, where data centres are also planned, saying the question was where Estonia’s electricity would come from and at what price.

Siim Kiisler, deputy leader of Parempoolsed, said data centre developers were watching electricity prices in Estonia. He said projects would only be built if they were financially viable at the expected price of electricity. Kiisler said the government should help create new power generation opportunities.

Source 