Court overturns €569,000 EU funding correction for Klaipėda

Saturday 21st November 2026 on 22:01 in Lithuania

Klaipėda city municipality does not have to repay a €569,000 financial correction for a project to renovate apartment-block courtyards, after Lithuania’s Supreme Administrative Court overturned the decision imposing it. The ruling was reported by LRT.

The court issued its final, unappealable ruling on October 28, annulling both a lower court decision that had rejected the municipality’s appeal and the Central Project Management Agency’s October 2023 decision to apply the correction. The agency must complete its investigation and issue a new decision.

The court agreed that the municipality had breached public procurement law and rules on changing contracts. But it said that finding a breach did not, by itself, establish that the EU budget had suffered or could have suffered harm. Any financial correction must be supported by specific circumstances showing an actual or potential adverse impact on the EU budget, the court said; the potential damage does not have to be calculated precisely.

The judges found that the agency had not explained how the breach could have affected the EU budget. The agency had imposed a correction equal to 10% of the construction contract’s value without assessing all the conditions required for doing so.

The municipality announced the contractor tender in November 2019 and signed a €5.694 million contract, including VAT, with the winning company, VVARFF, in January 2020. After the work deadline was extended, the contractor did not extend its civil liability insurance or other required guarantees. The documents expired about 15 months before construction was completed.

The agency said the municipality had effectively changed the contract terms by not requiring the contractor to extend its insurance and performance guarantee. It argued that this could have affected competition and given the contractor an unfair advantage. The agency also cited changes in economic and geopolitical conditions during the COVID-19 pandemic, deteriorating financial indicators at the contractor in 2021 and 2022, and increased insurance risk after the work was suspended for a total of 191 days.

The municipality argued that not requiring the documents had no effect on competition, the economic balance between the parties or the EU budget. It said the contractor’s insurance savings were small and the work was completed properly, making the correction disproportionate.