Riga committee delays decision on traffic during Vanšu Bridge reconstruction

Thursday 19th November 2026 on 16:45 in Latvia

Riga, transport, Vanšu Bridge

Riga City Council’s responsible committee has not decided how traffic will be organised during the reconstruction of Vanšu Bridge, LSM reported, citing Latvian Radio. The committee met for the first time on Thursday to identify issues to address before its next meeting.

Members did not determine whether the bridge would be fully or partly closed, or whether a temporary bridge would be built. The government backed the purchase of a larger modular bridge kit last week, which could be used during the reconstruction. The structures would remain in state reserves for use in crisis situations.

Building a temporary bridge would require a project, but the committee’s delay in making decisions also postpones the start of that work. Assembling the bridge structures would take about a month, while design work and installing supports would take longer.

The current order covers a bridge with one traffic lane. To make it a 450-metre bridge with two lanes for light vehicles, additional parts would be needed, said Martins Lazdovskis, head of the board of state-owned Latvijas Valsts ceļi. He did not know how much those parts would cost.

Committee members said they could readily obtain data on traffic volumes on Vanšu Bridge, drivers’ travel habits and the bridge’s performance. Several proposals were also raised, including diverting traffic away from the city centre.